Abel Tasman Sewage Management

bark bay

Bark Bay toilet

anchorage bay

Anchorage Bay Warden Hut

Akersten Bay

Akersten Bay

Kim Forbes, DoC Project Manager, and John Cocks and Paul Russell MWH project consultants

Techlink would like to thank the experts at the Department of Conservation and MWH (Montgomery Watson Harza) New Zealand Ltd, for their contributions to this case study.

Introduction

The Abel Tasman National Park has come under increasing pressure over recent years from international and domestic visitors who want to experience this unique natural environment. Annual visitor numbers now exceed 250,000 and the most popular hut and campsites have a visitor peak of between 1000 and 2000 visitors per day. It is now the most popular sea-kayaking destination in New Zealand and was recently voted, by a top rating UK publication, as one of the 10 best places in the world.

The Park's existing toilet facilities were not designed to meet the needs of growing numbers of visitors. The Department of Conservation (DOC) investigated sites where toilet facilities were at or near failure. Many of these had pit-privy toilets, while others had septic tanks with soakage fields. Problems identified with the toilet facilities included:

 

Background

Anchorage Bay

Anchorage Bay, one of the most popular sites in the Park, with up to 2 000 visitors per day at peak times.

Pumping Station

Finished pumping station at Anchorage Campground

Hut and Campground

Anchorage Hut and Campground – site layout plan

MWH was commissioned by the DOC to develop sustainable solutions for managing human waste and washing water at hut and camping sites in the Abel Tasman National Park (Conceptual statement). The solutions needed to be:

COP Brief Development

 

Planning

Anchorage campground

An elevated shot of the Anchorage Bay Campground shows the constrained nature of the site. At Anchorage, the largest campsite, there is limited flat open ground and the distance to the sea and adjacent wetlands are minimal.

pumping station

Anchorage Bay Campground pumping station

toilet block

Anchorage Hut toilet block

COP Planning for practice

Environmental Awareness

The first stage of the project included a review of the existing facilities and situation in the Park and an assessment of options for treating and controlling wastewater. DOC had a considerable amount of information on environmental issues within the park and other activities were undertaken to gather information including:

COP Outcome development and evaluation

Key information was presented to all stakeholders at a workshop.


An Iwi observor was present during all excavation work in areas sensitive to Iwi. An archaeologist was present in historically sensitive cultural sites and a DOC staff member and was onsite throughout construction. More about consultation.

 

Risk Assessment

storage pump

Installing the 22 000 buried septic tanks and storage pump at Anchorage Bay involved significant excavations. Visitor numbers at this site require capacity equivalent to a small community.

disposal field

Anchorage disposal field

pumping station

Anchorage Bay Campground – main pumping station

COP Planning for practice

Project risks were identified in partnership with DOC during the planning stages, and later during construction with the contractor.
A risk management strategy plan for the entire Park was developed. The following steps were taken during the planning stages to identify and assess project risks.

 

Design

new toilet

The new toilet at Akersten Bay is hidden in the bush immediately behind the beach. Its visual impact is minimal and its careful design ensures no uncontrolled discharges to sea.

COP Outcome development and evaluation

Work in the first stage identified a number of risk factors which resulted in further investigations.

Other risks identified and quantified included.

The design development also quantified and addressed the risk from system failure, remote location for servicing, high seasonal use, noise and other environmental constraints.

 

Development

Bark bay camp

Bark Bay Camp – site layout plan

septic tank

Bark Bay septic tank

buried septic tanks

The buried septic tanks and pump tank at Bark Bay are located only 0.5m above high water spring and required careful design and monitoring.

While the treatment of sewage need not be technically complex, the location of the project created a number of significant challenges to be addressed.

COP Outcome development and evaluation

 

Estimating projected user demand

The project included sites controlled by DOC and sites only accessed by kayakers and water skiers. Knowing accurate current and projected demand for toilet and washing facilities in the Park was critical to the success of the facilities design. As existing information was insufficient, DOC made the decision to delay the project for a season so that a detailed monitoring programme could be completed. Analysis of the information gathered enabled appropriate decisions to be made on the nature and capacity of the onsite treatment systems selected and the energy needed for pumping.

COP Planning for practice

Legislative requirements and constraints

A complex array of legislation applies to activities undertaken with the Park, including the National Parks Act, the Conversation Act, the Foreshore and Seabed Endowment Reinvesting Act, Historic Places Act, the Health Act, the Building Act, and the Resource Management Act. Relevant legislative requirements were identified in the Stage 1 sewage management 'issues and options' report and appropriate management procedures were determined and documented in the Sewage Management Plan.

COP Outcome development and evaluation

Cultural values

Historical occupation along the coastline by the tangata whenua meant there was potential risk associated with archaeological sites being disturbed or affected during the development and operation of wastewater facilities. The discharge of human waste is of particular concern to the tangata whenua. DOC representatives consulted extensively with Iwi to identify issues of concern and agree appropriate design and implementation requirements. During construction an Iwi observor an archaeologist and a DOC staff member were present to monitor the construction process and offer immediate advice in the event any archaeological sites were inadvertently disturbed.

 

Physical Environment Constraints

Onetahuti soakage trench

Onetahuti soakage trench

septic tank

Onetahuti completed septic tank

toilet diversion

Onetahuti toilet diversion

COP Brief development

Physical constraints included the generally low elevations of the hut and campsites, the proximity to coastal waters, estuaries or rivers, the bush-covered countryside, the sandy soils and estuarine sediments in coastal areas, the hilly topography, the limited areas of flat land, and in some places shallow rock. Site investigations characterised the physical constraints and on-site concepts were developed that were appropriate. Important aspects of the solutions were:

Access issues

Within the Park there are no infrastructural services such as roads, power supplies, telephones, water supplies and sewerage. Development in the Park needs to provide for such services during construction and in operation. Solutions adopted needed to have low water requirements, as natural supplies can be short-lived or run low during the summer. The provision of power reflected the needs of users at the site.

Aesthetic requirements

People go to National Parks to enjoy the natural environment. Developments, especially those for sewage management, need to minimise, as far as practicable, adverse aesthetic effects such as adverse visual effects, problem odours and noise. Solutions were designed to avoid or minimise visual effects, malodours and noise.

Ecological values

The Park contains native vegetation which must be protected. The introduction of weeds and the contamination of water during construction were unacceptable threats which were addressed through appropriate design and contractual requirements.

 

Economic constraints

The Park is isolated from conventional infrastructural services, so any development has the additional expense of transport and providing for other such services, during construction and operation. It was important for DOC that economically feasible ways were identified for providing for service and maintenance requirements. In addition, the operation of Park services could not be interrupted.

Innovative solutions adopted to minimise development and running costs included the use of duty and standby septic tanks, enabling considerable flexibility for pump-out events and providing overall financial benefits. The approach also reduces the risk of septic tank overflow, provides greater storage capacity in the event of pump malfunction and generally enhances the robustness of an onsite solution for a backcountry environment with high usage.

 

Innovative Solutions

Appletree Bay Nerski toilet cubicle

Paul Russel outside the Appletree Bay Nerski toilet cubicle. A solar ventilation chimney can be seen above the cubicle.

Septic tank effluent

Septic tank effluent is discharged via a series of drippers located in the slopes above the wetland behind the Anchorage Campground.

COP Outcome development and evaluation

Duty and stand-by septic tanks

Use of duty and stand-by septic tanks would deliver a number of environmental and economic benefits, including reducing the risk of septic tank overflow, providing greater storage capacity in the event of pump malfunction and generally enhancing the robustness of the solution. The dual septic tank system will also enable operators to manage toilet and washing facility discharges in a manner which avoids emergency pump-outs or the uncertainty of knowing when a septic tank will be full. The distribution manhole allows the hut warden to redirect flows simply when required. DOC has already benefited financially from this stand-by solution as expensive barge and associated pump-out facilities were not required during the 2001/2002 high season.

Solar power for pumps

Two types of solar powered effluent disposal systems were considered. The first involved a pump storage system where effluent was pumped to an elevated storage tank during hours of sunlight. The other involved storing electricity in batteries to enable pumping over a longer period. The latter system was selected and involved close liaison between electrical and sewage designers to optimise solar power availability, battery storage and emergency generation, sewage storage and peak use loading.

Ventilation enhanced vault toilets were installed at two locations because there was insufficient water for flushing or because the environment was unstable (sand dunes) and a removable, containment facility was considered the best solution. The vault toilet provides storage for several years. The system also includes a large, solar fan assisted ventilation system designed to avoid odours back-venting into the toilet cubicle. This was considered critical and has received much praise by users during the 2001/2002 season. The vaults have a detachable superstructure and both the vault and superstructure can be relocated by helicopter.

Toilets blocks have low flush toilets and waterless urinals to minimize water demand and to minimise hydraulic sewage load.

Subsurface, dripper effluent disposal systems were installed at the two largest sites. Dripper irrigation of septic tank effluent is a new technological system that enables effluent disposal in a controlled and sustainable way in a difficult topographical environment.

 

Project Success

Anchorage Bay generator

The Anchorage Bay generator was installed to provide backup power in the event the solar panels did not deliver sufficient power. The systen design ensures it is not used at night (when it would disrupt park users).

kitchen facilities

DOC Project Manager Kim Forbes enjoys the new kitchen facilities at the Anchorage Bay Campsite.

COP Outcome development and evaluation

The project was completed in time for the 2001/2002 summer season and was within the approved budget. Anecdotal evidence from DOC and visitors confirms the facilities provide an excellent level of service. To date the systems have proved reliable and are performing better than expected, particularly with respect to adequate storage and solar power performance. The buried dripper feed irrigation fields are disposing of the effluent without odour or runoff. Minor adjustment is to be undertaken at Bark Bay to balance pressures but monitoring has detected no adverse effects in the ground or surface waters.